| Date | Project | Details |
|---|
| since 1995 | Drafting of an expert's appraisal for numerous wind energy locations in relation to conflicts connected with nature conservation | |
| 2007 to 2008 | Construction of a coal-fired power station at the location Brunsbüttel: Accompanying landscape conservation plan, appropriate assessment of implications for a NATURA 2000 site and an assessment according to wildlife legislation | |
| 2007 to 2008 | Construction of a coal-fired power station at the location Stade-Bützfleth: Accompanying landscape conservation plan, appropriate assessment of implications for a NATURA 2000 site and an assessment according to wildlife legislation | |
| 2007 to 2008 | Construction of a coal-fired power station at the location Wilhelmshaven: Accompanying landscape conservation plan, appropriate assessment of implications for a NATURA 2000 site and an assessment according to wildlife legislation | |
| 2007 to 2008 | Construction of a coal-fired power station at the location Stade (former nuclear power station): Environmental screening | |
| 2006 to 2008 | Operation of four dams at feed and discharge of the ‘Großes Meer' in context of the new water management concept for the ‘Großes Meer' and the regional development concept ‘Meer erleben – Mehr verstehen' (‘Experience the sea – Learn more'): Preparation of documentation for a water legislation procedure (based on concept planning and carried out in cooperation with the NLWKN Aurich) | |
| 2007 | Platforms at the western shore of the ‘Mahlbusens' in Dornumer-/Westeraccumersiel: Detailed report within the frame of the application for water legislation approval with accompanying landscape conservation plan, appropriate assessment of implications for a NATURA 2000 site and analysis of compatibility according to wildlife legislation | |
| 2007 | Resting pier for water hikers at ‘Dornumersieler Tief' in Dornum: Detailed report within the frame of the application for water legislation approval with accompanying landscape conservation plan | |
| 2007 | Environmental impact study, accompanying landscape conservation plan and appropriate study of implications for a NATURA 2000 site for flood control at the river Ems for the planned impounding weir ‘Mühlenbach' at the town area of Lingen | |
| 2006 | Appropriate pre-assessment of implications for a NATURA 2000 site for the ‘3-Meere-Weg' (3-Seas-Pathway) at ‘Großes Meer' in the context of the project 'Meer erleben - Mehr verstehen' (‘Experience the sea – Learn more') | |
| 2003 to 2004 | Ecological construction supervision and landscape management planning for selected parts of the 2nd construction phase of the railway line ‘Hamburg – Berlin' in Brandenburg (in cooperation with PAN Potsdam) | Details |
| 2000 to 2004 | Accompanying construction analysis of impacts on resting birds in the area of the outer port of Emden | |
| 2003 | Appropriate analysis of implications for a NATURA 2000 site for the ‘Maritimen Ferienpark Parow' (‘Maritime Holiday Park Parow') | |
| 2001 to 2003 | Environmental impact study with an integrated appropriate study of implications for a NATURA 2000 site and an accompanying landscape conservation plan for the removal of 10 railway conversions in relation to the 2nd construction phase of the railway line ‘Hamburg – Berlin' in Brandenburg (in cooperation with PAN Potsdam) | |
| 1994 to 2003 | Environmental impact study and accompanying landscape conservation plan: Flood control at the town Lingen (Ems) | Details |
| 2000 to 2001 | Environmental impact study following the regional planning procedure for the planned aquatic sports centre ‘Schwedenschanze' at the Hansatic City of Stralsund (in cooperation with PAN) | |
| 2001 | Location appraisal concerning the conflict between wind energy and birds for 12 planned wind parks in Campania and Calabria at Southern Italy | Details |
| 1991 to 2000 | Environmental impact study with an integrated accompanying landscape conservation plan for the 1st construction phase of the railway line ‘Hamburg – Berlin' in Brandenburg (partially in cooperation with NWP Oldenburg and PAN Potsdam) | Details |
| 1998 to 2000 | Cross-border compatibility study for a wind park at the German-Dutch border area (in cooperation NWP Oldenburg) | |
| 1997 to 1998 | Conception and coordination of faunistic surveys for the development of the federal motorway 44 (in cooperation with Bosch & Partner in Mooseurach) | |
| 1997 to 1998 | Technical nature conservation consulting and assessment of the environmental needs in the context of regional planning procedure and plan approval procedure: Development of the ‘Unteren-Havel-Wasserstraße' (‘Lower-Havel-Waterway') in Brandenburg | Details |
| 1997 to 1998 | Environmental impact study and accompanying landscape conservation plan: Enhancement of the wastewater treatment plant in Lingen (Ems) | |